Carpentry
• Music rooms casework installations completed
• Music rooms acoustic wall panels completed
• PAC stage flooring ongoing
•PAC ceiling finishes ongoing
• PAC acoustic wall panels ongoing
• West locker rooms flooring and ceiling tile installations completed
• Main Gymnasium flooring installation ongoing
• Kitchen corridors and support spaces ceiling tile installation ongoing
• High School & Junior High main entrance steel canopies completed
• Board Office areas flooring installation completed
• Board Office casework installation ongoing
• Student dining area ceiling grid installation ongoing
• JH locker rooms flooring and ceiling grid installations completed
• Junior High first floor ceiling grid and tile completed
• Junior High second floor flooring and ceiling tile installations completed
• Junior High first floor flooring installation ongoing
• High School first and second floors commons area flooring completed
• Junior High first floor ceiling grid and MEP finishes completed
• Junior High first floor ceiling tile installation completed
• Junior High second floor ceiling tile installations completed
• Junior High second floor flooring installation completed
• Junior High first floor flooring installation ongoing
• Junior High first floor casework installation ongoing
• Junior High second floor casework installation ongoing
Misc. Finishes
• Furniture deliveries ongoing
• High School first floor classroom furniture setup completed
• High School second floor classroom furniture set up completed
• Kitchen equipment installations ongoing
Concrete & Courtyard area
• Sitework concrete and pavement installations completed
• Student courtyard decorative gravel installation completed
Mechanical, Plumbing & Electric
• HVAC start-ups completed
• Student dining areas above ceiling MEP rough-ins completed