Carpentry

• Student Courtyard Concrete Installation completed
• Junior High Second Floor Ceiling Grid completed
• High School First and Second Floor Casework Installations completed
• Junior High First and Second Floor Ceiling Grid Installations completed
• Kitchen/Serving Areas Ceiling Grid Installation completed
• Kitchen/Serving Areas Ceiling Grid Installation completed
• Music Rooms Casework Installations ongoing
• PAC Ceiling Finishes ongoing
• Music Rooms Acoustic Wall Panels ongoing
• Junior High First Floor Ceiling Grid ongoing
• Junior High Second Floor Ceiling Tile Installations ongoing

Misc. Finishes

• Kitchen Serving Areas Epoxy Flooring Installation completed
• Main Gymnasium Gym Equipment Installations completed
• South Locker Rooms Flooring Installation completed
• Kitchen Serving Areas Epoxy Flooring Installation completed
• Main Gymnasium Gym Equipment Installations completed
• Elevator and Wheelchair Lift Installations completed
• Board of Education First and Second Floor Porcelain Tile at Bathrooms completed
• Board of Education Office Areas Ceiling Grid and Tile Installations completed
• Furniture Deliveries ongoing
• PAC Stage Flooring ongoing
• West Locker Rooms Flooring Installations ongoing
• High School & Junior High Main Entrance Steel Canopies ongoing
• High School First and Second Floors Commons Area Flooring ongoing

Concrete & Courtyard area

• Student Dining Stairs Installation and Concrete Infill completed
• Site Concrete sidewalks and pavement Installations ongoing
• Student Courtyard Decorative Gravel Installation ongoing

Plumbing & Electric

• Main Gymnasium Overhead MEP Installations completed
• South and West Locker Rooms Plumbing Fixture Installations completed
• Junior High First and Second Floor Above Ceiling MEP Rough Ins completed
• Student Dining Areas Above Ceiling MEP Rough Ins ongoing
• Junior High First Floor MEP Finishes ongoing

June22Construction