Carpentry

• Performing Arts Center (PAC) stage area rigging and equipment installation completed
• Elevator installation ongoing
• PAC back of house and music rooms ceiling grid completed
• High School and Auxiliary locker rooms ceiling grid installations completed
• High School main entrance exterior wall framing completed
• Board Office and first floor ceiling grid installations completed
• High School second floor drywall finishing completed
• Junior High first floor hang drywall completed
• Junior High first floor finish drywall completed
• High School first floor ceiling grid completed
• Junior High second floor ceiling grid completed
• Junior High first floor ceiling grid completed
• Kitchen/Serving areas ceiling grid installation ongoing
• Junior High first and second floor ceiling grid installations ongoing

Misc. Finishes

• High School second floor wall painting completed
• Junior High first floor wall painting completed
• Junior High locker rooms wall painting ongoing
• High School first floor classroom flooring completed
• Junior High gymnasium wood flooring installation ongoing
• High School gymnasium equipment installations ongoing
• Board Offices & High School first and second floor porcelain tile at bathrooms ongoing
• Junior High first and second floor porcelain tile at bathrooms ongoing

Masonry/Concrete

• Sitework concrete and pavement installations ongoing
• Student courtyard concrete installation ongoing
• High School entrance CMU veneer completed
• Junior High exterior CMU veneer completed

Plumbing & Electric

• Kitchen fume hoods and ductwork installations completed
• Junior High first and second floor above ceiling MEP rough-ins ongoing

ConstructionUpdateMay22