Concrete
• Junior High second story concrete floor pour is complete
Masonry
• Junior High east wall CMU veneer is complete
• Junior High second floor interior CMU wall construction ongoing
• High School and Junior High east wall brick veneer ongoing
Structural Steel
• Student Dining Area structural steel installation is complete
• Student Dining Area structural steel and decking installations is complete
Roofing
• Music Rooms roof detailing is complete
• Junior High roof detailing is complete
• Junior High Gymnasium roof detailing is complete
• High School Gymnasium roof detailing is complete
• Auxiliary Gymnasium roof detailing is complete
• Junior High roofing system installation ongoing
• Board Offices high and low roof system installations ongoing
Plumbing & Electric
• Gas service to the building is complete
• High School first and second floor in-wall mechanical, electrical, and plumbing (MEP) rough-ins are complete
• High School first and second floor overhead and in-wall MEP rough-ins ongoing
• Junior High Air Handling Unit installations are complete
• Rooftop HVAC unit installations are complete
• Electric service to the building is complete
• Junior High in-wall and overhead MEP rough-ins ongoing
• Junior High gymnasium overhead MEP rough-ins ongoing
• Main gymnasium overhead MEP installations ongoing
• Auxiliary gymnasium overhead MEP installations ongoing
Carpentry
• Junior High window installations is complete
• Junior High exterior wall framing is complete
• High School second floor insulation and drywall installations ongoing
• Music rooms doors and windows installations ongoing
• Performing Arts Center partition wall framing ongoing