Concrete

• Junior High second story concrete floor pour is complete

Masonry
 Junior High east wall CMU veneer is complete
 Junior High second floor interior CMU wall construction ongoing
 High School and Junior High east wall brick veneer ongoing

Structural Steel
 Student Dining Area structural steel installation is complete
 Student Dining Area structural steel and decking installations is complete

Roofing
 Music Rooms roof detailing is complete
 Junior High roof detailing is complete
 Junior High Gymnasium roof detailing is complete
 High School Gymnasium roof detailing is complete
 Auxiliary Gymnasium roof detailing is complete
 Junior High roofing system installation ongoing
 Board Offices high and low roof system installations ongoing

Plumbing & Electric
 Gas service to the building is complete
 High School first and second floor in-wall mechanical, electrical, and plumbing (MEP) rough-ins are complete
 High School first and second floor overhead and in-wall MEP rough-ins ongoing
 Junior High Air Handling Unit installations are complete
 Rooftop HVAC unit installations are complete
 Electric service to the building is complete
 Junior High in-wall and overhead MEP rough-ins ongoing
 Junior High gymnasium overhead MEP rough-ins ongoing
 Main gymnasium overhead MEP installations ongoing
 Auxiliary gymnasium overhead MEP installations ongoing

Carpentry
 Junior High window installations is complete
 Junior High exterior wall framing is complete
 High School second floor insulation and drywall installations ongoing
 Music rooms doors and windows installations ongoing
 Performing Arts Center partition wall framing ongoing