Early Site Package:

• ADA ramp to baseball field concrete work was completed
• Baseball field sod placement is nearing completion
• Bleachers & press boxes were completed for both the softball and baseball fields
• The asphalt drive to the baseball field was completed
• The cubbies in all dugouts were completed
• The net systems for the batting cages was completed
• Final grade and seed are in progress

Building Package:
Masonry
• Courtyard CMU veneer is complete
• Performing Arts Center seating area interior CMU walls is complete
• Music Rooms non-bearing interior CMU walls is complete
• South Locker Rooms non-bearing interior CMU walls is complete
• West Locker Rooms non-bearing interior CMU walls is complete
• High School (HS) north wall CMU veneer ongoing
• Junior High (JH) east wall CMU veneer ongoing

Structural Steel
• JH structural steel and decking installations are complete
• Dining area structural steel installation ongoing

Roofing
• HS roofing system installation is complete
• Music Rooms roofing system installation is complete
• Main Gym/North and South Mezzanines roofing system installation is complete
• JH Gym roofing system installation is complete
• Auxiliary Gym roofing system installation is complete
• Main Mechanical and Electrical Rooms roofing system installation is complete
• Area 3 roofing system installation ongoing

Plumbing & Electric
• JH above ceiling mechanical, electrical, and plumbing (MEP) rough-ins at first and second floors are complete
• Main Gym Overhead MEP rough-ins ongoing
• JH first and second floor overhead MEP rough-ins ongoing
• JH first and second floor in wall MEP rough-ins ongoing
• HS first and second floor in wall MEP rough-ins ongoing

Carpentry
• HS interior wall framing at first and second floors is complete
• HS exterior wall framing is complete
• HS and JH window system installations ongoing

ConstructionUpdate12 3 21 1ConstructionUpdate12 3 21 2