Early Site Package:
Baseball & Softball Fields
• Foul ball poles have been installed on both fields
• Scoreboards for both fields have been installed
• Benches in the dugouts are currently being installed
• Both fields have been prepped and for sod
• Sod installation began week of 9/27
• Irrigation systems will be final tested this week
• Press boxes have been delivered
ADA Access Ramp
• The ADA Ramp is progressing. Beaver continues to form and pour sections of the walls. Once the walls are done they will start the stair sections and slabs on grade.
Building Package:
Concrete
• Area 5 second floor concrete slab placement completed
• JH gymnasium concrete slab on grade placement completed
• Main gymnasium concrete slab on grade placement completed
Masonry
• Main gymnasium CMU veneer at exterior walls completed
• JH gymnasium CMU veneer at exterior walls completed
• Music rooms CMU and brick veneer installations ongoing
Structural Steel
• In-wall MEP rough-in at Area 3 board office partition walls completed
• Area 5 structural steel and decking installation completed
• Area 6 structural steel installation completed
• JH gymnasium steel bar joist installations completed
• Main gymnasium steel bar joist installations completed
• Auxiliary gymnasium steel bar joist installations completed
• Main mechanical and main electrical rooms steel bar joist and decking installations completed
• Area 6 structural roof decking installations ongoing
• Main gym/JH gym/Auxiliary gym structural roof decking installations ongoing
• Music rooms structural steel roof bar joist and roof decking installations
Roofing
• West locker rooms roof system installation completed
• Performing Arts Center stage area roof system installation completed
• Performing Arts Center seating area roof system installation completed
Plumbing & Electric
• South Locker Rooms above-ceiling MEP rough-in completed
• Kitchen and Serving Areas above ceiling MEP installations ongoing
• Area 3 above ceiling MEP rough ins ongoing
• Area 5 above ceiling MEP rough ins ongoing
Carpentry
• Exterior and interior wall framing at Area 3 board offices completed
• Area 5 interior and exterior wall framing ongoing