𝐄𝐚𝐫𝐥𝐲 𝐒𝐢𝐭𝐞 𝐏𝐚𝐜𝐤𝐚𝐠𝐞
𝐂𝐨𝐧𝐜𝐞𝐬𝐬𝐢𝐨𝐧𝐬 𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠
• Above ceiling electrical rough-in has been completed.
• The electrical room panels and transformer have been installed and wired.
• Lighting suspended in the acoustic grid and has been installed.
• Above ceiling mechanical has been completed.
• Toilet chase rough-in and above ceiling rough-in has been completed.
• Interior walls have been cleaned and painted.
• Drywall ceilings have been hung.
• Acoustical ceiling grid has been laid out and installed.
• Concrete frost slabs have been poured.
• Irrigation system supply piping is being installed.
𝐃𝐮𝐠𝐨𝐮𝐭𝐬
• Metal roofing, trim & downspouts are nearing completion.
• Masonry has been painted.
• Concrete slabs/frost slabs have been poured.
• Doors and hardware have been installed.
𝐄𝐥𝐞𝐜𝐭𝐫𝐢𝐜𝐚𝐥 𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠
• Metal roofing, trim & downspout are nearing completion.
• Concrete frost slab was poured.
• Door opening is being prepped for door and hardware placement.
𝐒𝐢𝐭𝐞𝐰𝐨𝐫𝐤
• All storm piping has been completed.
• Storm structure inverts have been poured.
• The Bio-Retention pond at 546 has been excavated and media has been placed.
• Fine grade and topsoil have been placed on the south side of the property, around the detention pond and on the majority of the soccer fields.
• Grass seed is placed on the south side of the property and around the detention pond. Seed placement will continue north towards the new school building.
• The fire lane on the east side of the new school has been cut to grade and stoned.
• Installation of site conduits from the concession building to the dugouts, scoreboards, and future ball field lighting is in progress.

𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐏𝐚𝐜𝐤𝐚𝐠𝐞
𝐂𝐨𝐧𝐜𝐫𝐞𝐭𝐞
• Elevator shaft foundations/pit slab and pit walls are complete.
• SOG prep and pour at Area 3 (admin) area is ongoing.
• SOG prep at Area 5 (high school academic) area is ongoing.
𝐌𝐚𝐬𝐨𝐧𝐫𝐲
• CMU at PAC/stage north and west walls are complete.
• CMU from top of footing to FF elevation at entire perimeter of building is complete.
• Structural steel column base plates and grout is complete.
• CMU to roof height at Area 2 main electrical room is complete.
• Masonry veneer at PAC/stage north and west walls is ongoing.
• CMU at PAC/stage south wall is ongoing.
• CMU at main gymnasium walls is ongoing.
• CMU at JH gymnasium north and east walls is ongoing.
𝐏𝐥𝐮𝐦𝐛𝐢𝐧𝐠
• Standard Plumbing has continued with the below slab installation of the sanitary lines, storm lines and acid waste lines in the Administration area, the kitchen, and education areas.
• Standard Plumbing has been working with Valentine Masonry coordinating all wall sleeves for future pipe installations and all wall openings for future duct installation.
𝐄𝐥𝐞𝐜𝐭𝐫𝐢𝐜
• Speelman Electric has continued with the below slab installation of the feeder conduits from the main electrical rooms to sub locations and then all of the branch circuits for distribution.
• Speelman Electric has been working with Valentine Masonry coordinating all of the in- wall conduits for lighting, power, equipment, etc. as required.
• Speelman Electric has excavated, placed and backfilled site electrical conduits from the main building down the access road to Route 546. They have placed the light pole bases down the access road to Route 546.